This example is based on the Natural Depletion Example but in this case chokes have been included to constrain the flow rate. For illustrative purposes, it is assumed that the constraint is 9,000 bbl/d. The predicted gas and oil flow rates are shown below. It can be seen that plateau production is maintained for about 4 years. This simulation also takes about 40 seconds to complete.
Example of a Constrained Depletion LOF Model of a 3 Well Development